Joliet City Logo
File #: TMP-2328    Name:
Type: Consent Agenda Status: Agenda Ready
File created: 8/30/2021 In control: Public Service Committee
On agenda: 9/7/2021 Final action:
Title: Change Order No. 4 for the 2020 Sanitary Sewer Rehabilitation Program to Performance Pipelining Inc. in the amount of $28,508.55
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                           Mayor and City Council

 

FROM:                      James V. Capparelli, City Manager

 

SUBJECT:

title

Change Order No. 4 for the 2020 Sanitary Sewer Rehabilitation Program to Performance Pipelining Inc. in the amount of $28,508.55

end

 

BACKGROUND:

On January 7, 2020, the Mayor and City Council awarded a Contract for the 2020 Sanitary Sewer Rehabilitation Program, in the amount of $7,870,480.96, to Performance Pipelining Inc.  Subsequently, the Mayor and City Council have approved Change Orders No 1 - 3 in the amount of $192,214.95.  The Public Service Committee will review this matter.

 

CONCLUSION:

Change Order No. 4, a net increase in the amount of $28,508.55, is for the following work:

 

                     Additional lateral preparation work for CIPP

                     Additional topside manhole work

                     Modification of 1,300 vertical feet of 36-inch cementitious coating work to 48-inch cementitious coating work

                     Balancing of quantities

 

Funds will be charged to the Water & Sewer Improvement Fund / IEPA Loan / Construction (Org 51680000, Object 557200, $28,508.55.

 

RECOMMENDATION:

recommendation

Based on the above, the Administration recommends that the Mayor and City Council approve Change Order No. 4, a net increase in the amount of $28,508.55, on behalf of Performance Pipelining Inc.

end