File #: 392-22    Name:
Type: Consent Agenda Status: Passed
File created: 7/21/2022 In control: City Council Meeting
On agenda: 8/2/2022 Final action: 8/2/2022
Title: Change Order No. 7 in the amount of ($699,403.03) and Final Payout in the amount of $765,710.58 for the 2020 Sanitary Sewer Rehabilitation Program to Performance Pipelining Inc.
Attachments: 1. Approver Report

TO:                                           Mayor and City Council

 

FROM:                      James V. Capparelli, City Manager

 

SUBJECT:

title

Change Order No. 7 in the amount of ($699,403.03) and Final Payout in the amount of $765,710.58 for the 2020 Sanitary Sewer Rehabilitation Program to Performance Pipelining Inc.

end

 

BACKGROUND:

On January 7, 2020, the Mayor and City Council awarded a Contract for the 2020 Sanitary Sewer Rehabilitation Program, in the amount of $7,870,480.96, to Performance Pipelining Inc.  Subsequently, the Mayor and City Council have approved Change Orders No. 1 - 6 for a total amount of ($1,245.07).  The Public Service Committee reviewed this memo at the July 18, 2022, meeting and recommended for approval by Full Council.

 

CONCLUSION:

Change Order No. 7, a net decrease in the amount of ($699,403.03), is for the following work:

 

                     Schwalm robot mainline wrap cutting to complete lateral lining work

                     Lateral liner cutting from an exterior cleanout to prevent an excavation repair on private property.

                     Balancing of quantities for the final payout.

 

Funds will be credited to the Water & Sewer Improvement Fund / IEPA Loan / Construction (Org 51680000, Object 557200, ($699,403.03)).

 

The Contractor has also requested a 39-day extension for final completion, due to difficulties coordinating the punchlist work with homeowners.  City staff recommends the 39-day extension of final completion, which will allow time for the contractor to coordinate the remaining punch list items with the homeowners.  Change Order No. 7 will extend the contract by 39 days.  The revised final completion date is July 12, 2022.

 

In addition, Payment No. 18 and Final, in the amount of $765,710.58, is presented for approval on behalf of Performance Pipelining Inc.

 

RECOMMENDATION:

recommendation

Based on the above, the Administration recommends that the Mayor and City Council take the following actions:

 

1.                     Approve Change Order No. 7, a net deduction in the amount of ($699,403.03) and grant a 39-day extension on final completion for the 2020 Sanitary Sewer Rehabilitation Program, on behalf of Performance Pipelining Inc.

 

2.                     Approve Payment No. 18 and Final, in the amount of $765,710.58, on behalf of Performance Pipelining Inc.