File #: 393-22    Name:
Type: Consent Agenda Status: Passed
File created: 7/21/2022 In control: City Council Meeting
On agenda: 8/2/2022 Final action: 8/2/2022
Title: Change Order No. 1 in the amount of ($690.00) and Final Payout in the amount of $4,154.00 for the Fairmont and Garvin Sanitary Improvement Project to Performance Construction and Engineering
Attachments: 1. Approver Report

TO:                                           Mayor and City Council

 

FROM:                      James V. Capparelli, City Manager

 

SUBJECT:

title

Change Order No. 1 in the amount of ($690.00) and Final Payout in the amount of $4,154.00 for the Fairmont and Garvin Sanitary Improvement Project to Performance Construction and Engineering

end

 

BACKGROUND:

On March 1, 2022, the Mayor and City Council awarded a Contract for the Fairmont and Garvin Sanitary Improvement Project, in the amount of $42,230.00, to Performance Construction and Engineering.  The Public Service Committee reviewed this memo at the July 18, 2022, meeting and recommended for approval by Full Council.

 

CONCLUSION:

Change Order No. 1, a net decrease in the amount of ($690.00) is for the following work:

 

                     Balancing of quantities for final payout.

 

Funds will be credited to the Water and Sewer Improvement Fund (Org 50180020, Object 557200, ($690.00).

 

In addition, Payment No. 2 and Final, in the amount of $4,154.00, is presented for approval on behalf of Performance Construction and Engineering.

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council take the following actions:

 

1.                     Approve Change Order No. 1, a net deduction in the amount of ($690.00), for the Fairmont and Garvin Sanitary Improvement Project on behalf of Performance Construction and Engineering.

 

2.                     Approve Payment No. 2 and Final, in the amount of $4,154.00, on behalf of Performance Construction and Engineering.